Tuesday, May 26, 2009

Almost all equpiment transported!!

On 24th May 2009, after spending almost an entire day confirming the status of the equipment, on 25th May, we finally transported almost all equipment to the village. A truck arrived in the outskirts of Kathmandu Valley to pick up equipment including tin roof to complete the construction of the Power House, cement and sand to construct the foundation of the Peltric Set, 420m of High Density Polyethylene Pipe from Nepal Poly Pipe for Penstock and Peltric Generating Set from Power Tech Nepal. Dr. Nepali coordinated and led the truck team to various locations where all the equipment and materials were picked up from. Special thanks to him without whose generous help, the all-day-long endeavor would have been impossible.